All courses › Building and Structures
Building and Structures: free practice, theory and problems
Before you can design a beam or a floor, you need to know which loads it must carry. In Norway we follow the Eurocodes (NS-EN 1990 and 1991). You split the loads into permanent and variable loads, turn area loads into line loads on the beams, and apply safety factors.
Contents
1. Loads and load combinations
What is it about?
Before you can design a beam or a floor, you need to know which loads it must carry. In Norway we follow the Eurocodes (NS-EN 1990 and 1991). You split the loads into permanent and variable loads, turn area loads into line loads on the beams, and apply safety factors.
In short
- Permanent load : the self-weight of the structure, floors, roof and fixed installations. Computed from thickness and unit weight, for example concrete 25 kN/m³.
- Variable load : imposed load from people and furniture (housing 2.0 kN/m², offices 3.0 kN/m²), snow and wind.
- Snow load on a roof: , where is the ground snow load for the site and the shape factor for a flat roof.
- From area load to line load: a beam carries the load from a strip as wide as the spacing :
- Ultimate limit state (simplified, one dominant variable load): the loads are multiplied by load factors.
- Simply supported beam with a uniform load: and support reaction .
Which loads act on a building?
- Permanent loads (self-weight, ): the weight of the structure itself and fixed equipment – concrete about 25 kN/m³, steel about 78.5 kN/m³, timber about 5 kN/m³. They can be calculated fairly precisely.
- Imposed loads (): people, furniture and storage. Given in the standard by category of use – for example around 2 kN/m² for dwellings and 3–5 kN/m² for offices, assembly areas and storage, depending on use.
- Snow load: , where is the characteristic ground snow load for the municipality (from under 2 to over 10 kN/m² in Norway, highest inland and in the mountains) and is a shape coefficient for the roof. Steep roofs hold less snow; at changes in roof height and roof structures drifts can give much higher loads.
- Wind load: depends on the site's reference wind speed, terrain category, height above ground and building shape. Wind gives both pressure and suction – suction on roofs and corners often tears off roofing.
- Also: earth pressure, water pressure, thermal loads, earthquakes and accidental loads (impact, explosion, fire).
Limit states
Eurocode 0 (NS-EN 1990) is based on the limit state method:
- Ultimate limit state (ULS): the structure must not collapse. Loads are increased by partial factors, and material strength is reduced.
- Serviceability limit state (SLS): the structure must perform well in use – limits on deflection, vibration and cracking. Here loads are used without (or with smaller) factors.
Load combinations
Since all variable loads are unlikely to act at full strength simultaneously, they are combined: one leading variable load is taken in full, the others are reduced by combination factors . A typical ULS combination is
and several combinations with different leading loads must be checked, taking the worst. When self-weight acts favourably (for example against overturning or uplift), a low factor (0.9 or 1.0) is used. In Norway the National Annex sets the factors to use.
Load path
A good structural engineer follows the load path: from the roof and floors via beams and columns or load-bearing walls down to the foundations and the ground. All loads – including horizontal wind loads – need a continuous path to the ground. Horizontal bracing (diaphragms, cross-bracing, cores) is as important as carrying vertical load.
How to solve the problems
- Find the area loads in kN/m² (self-weight and imposed load separately).
- Multiply by the spacing to get a line load in kN/m.
- Combine with the load factors.
- Compute the moment and support reactions for the beam.
Example
Floor joists in a house: self-weight 0.5 kN/m², imposed load 2.0 kN/m², spacing 0.6 m and span 4.0 m.
- kN/m and kN/m.
- kN/m.
- kNm.
Common mistakes
- Forgetting to multiply the area load by the spacing.
- Applying the load factor twice, or forgetting it.
- Mixing kN and N, or mm and m, in the moment formula.
Concepts in this part
2. Building physics: heat and moisture
What is it about?
A good house keeps the heat in, the moisture out and the electricity bill low. Building physics is about how heat and moisture pass through walls, roofs and windows. The Norwegian building regulations (TEK17) set requirements for how well each part must be insulated.
In short
- Thermal resistance of a layer with thickness and thermal conductivity (W/mK):
- U-value (thermal transmittance) of the whole construction. The resistances are added, including the surface resistances inside () and outside ():
- Heat loss through a surface: (W). Energy: power times time, .
- TEK17 requirements (U-value): external wall ≤ 0.18, roof ≤ 0.13, windows ≤ 0.80 W/m²K.
- Moisture: warm air can hold more water vapour than cold air. If air is cooled below the dew point, the vapour turns into water (condensation). That is why the vapour barrier is placed on the warm side of the insulation.
Heat transfer
Heat always flows from warm to cold, in three ways: conduction through materials, convection with moving air (including air leaks) and radiation. A material's insulating ability is given by its thermal conductivity (W/mK): mineral wool about 0.035, timber about 0.12, concrete about 2. Insulation works because it traps still air.
U-value
A construction with several layers has thermal resistance plus surface resistances inside and outside. The U-value is (W/m²K), and the heat loss is
TEK17 (the Norwegian building regulations) sets energy requirements and minimum values such as external walls , roofs , floors and windows W/m²K. Windows remain the weakest point in most buildings.
Thermal bridges and airtightness
- Thermal bridges are places where heat escapes more easily – continuous concrete in balconies, steel beams, studs and corners. They cause heat loss, cold interior surfaces and a risk of condensation and mould.
- Airtightness: leaky buildings lose a lot of heat and can suffer moisture damage when warm, humid indoor air leaks out. It is measured by a blower-door test as the air change rate ; TEK17 requires at most 0.6 air changes per hour at 50 Pa.
Moisture
Air can hold more water vapour the warmer it is. Relative humidity (RH) is the ratio of actual to maximum moisture at that temperature. When air cools, RH rises, and at the dew point (100 %) water condenses. Mould can grow at RH above about 75–80 % over time.
Principles of a moisture-safe external wall in a cold climate:
- A vapour barrier (plastic membrane) on the warm inside stops humid indoor air from entering and condensing in the cold part of the wall. It must be sealed at joints and around penetrations.
- A wind barrier outside the insulation stops cold wind from blowing through the insulation, but must be vapour-open so moisture can dry out.
- Ventilated cladding with an air gap behind lets driving rain that gets past the cladding run down and dry out – two-stage protection.
- Rule of thumb: the construction should be at least 10 times tighter to vapour on the inside than on the outside, so moisture that gets in can get out.
Sources of moisture
Construction moisture (concrete must dry before flooring), precipitation and driving rain, ground moisture (capillary suction – hence capillary-breaking layers under slabs), leaks and indoor moisture from showers, cooking and people. Good ventilation removes moisture and pollutants from inside.
How to solve the problems
- Compute for each layer (thickness in metres).
- Add all the resistances, including and .
- , and the heat loss is .
Example
A wall has 200 mm of insulation with W/mK. Ignore the other layers.
- m²K/W.
- m²K/W.
- W/m²K, which meets the 0.18 requirement.
Common mistakes
- Using the thickness in mm instead of m.
- Adding U-values instead of R-values. It is the resistances that add up.
- Putting the vapour barrier on the cold side. Then moisture can condense inside the wall.
Concepts in this part
3. Surveying
What is it about?
Before a road, a building or a tunnel can be built, the terrain must be surveyed and the structure set out in the right place. Surveying is about coordinates, distances, directions and heights.
In short
- Norwegian maps use coordinates north () and east () in metres. The distance between two points:
- Angles in surveying are often measured in gon: a full circle is 400 gon (versus 360°). A right angle is 100 gon.
- Levelling: you read a staff at the back point (known height) and at the front point. The height difference is
- Gradient in percent: .
- Scale 1 : : 1 cm on the map is cm in the terrain. At 1 : 1000, 1 cm is 10 m.
- Area from coordinates (shoelace formula) for a polygon with corners :
Why surveying?
Everything built must be placed correctly: on the right plot, at the right height and with the right shape. Surveying (geomatics) covers measuring what exists (terrain, existing buildings, utilities) and setting out what is to be built (corners, axes, levels). Setting-out errors can be very expensive.
Coordinate systems and heights
- Norway uses EUREF89 as the geodetic datum, with the map projection UTM (zones 32, 33 and 35) or NTM (Norwegian Transverse Mercator, with narrower zones and smaller scale error, widely used in construction).
- Coordinates are given as north (N, x) and east (E, y). Note that surveyors traditionally use x towards north – the opposite of mathematics.
- Heights are given in the NN2000 height system, based on mean sea level. Satellite measurements give height above an ellipsoid, which must be corrected with a geoid model to get height above sea level.
Instruments and methods
- Levelling: a level gives a horizontal line of sight, and readings are taken on a staff at two points. The height difference is the backsight minus the foresight. Very accurate, to the millimetre.
- Total station: measures horizontal angle, vertical angle and distance (by laser). From a known station, coordinates of new points are calculated by polar calculation: , , where is the bearing from north.
- GNSS (GPS, Galileo, GLONASS, BeiDou): simple receivers give metre accuracy; with RTK (real-time corrections from base stations, for example CPOS from the Norwegian Mapping Authority) 1–3 cm is achieved. Works poorly under trees, near tall buildings and in tunnels.
- Laser scanning and drones with photogrammetry give point clouds and detailed 3D models of terrain and buildings.
Angles and direction
Surveyors often use gon (400 gon in a full circle), not degrees. 100 gon = 90°. Bearings are measured clockwise from north.
Errors and checks
All measurements contain errors: gross errors (misreading, wrong point), systematic errors (calibration, temperature) and random errors. That is why measurements are always checked: back to a known point, redundancy (more measurements than needed) and adjustment by least squares. A traverse that starts and ends at known points reveals if something is wrong.
From measurement to model
Measurements feed into BIM and machine control: excavators and pavers with GNSS can work directly from the 3D model, without pegs in the ground.
How to solve the problems
- Compute the differences and between the points.
- Use Pythagoras for distance, and remember that levelling gives back minus front.
- Convert scale by multiplying up and then changing unit.
Example
Point A has a height of 12.345 m. The staff reading at A is 1.200 m and at B 0.800 m.
- m. Positive, so B is higher.
- m.
Common mistakes
- Computing front minus back in levelling, which gives the wrong sign.
- Mixing degrees and gon.
- Forgetting to convert cm on the map to metres in the terrain.
- Trusting a single measurement. Check measurements, such as a closed loop, reveal errors.
Concepts in this part
Example problems with solutions
Here are some of the problems in building and Structures. In the app, calculation problems get new numbers every time, so you can practise until it sticks – and take a practice exam with an indicative grade as you prepare for the exam.
Loads and load combinations: A floor has an imposed load of 2.0 kN/m². The beams are spaced 0.6 m apart. What line load does each beam get from the imposed load?
Answer: 1.2 kN/m
kN/m.
Building physics: heat and moisture: What is the thermal resistance of 200 mm of insulation with W/mK?
Answer: 5.556 m²K/W
m²K/W.
Surveying: Point A has the coordinates N = 100, E = 200 and point B N = 130, E = 240 (metres). How far apart are the points?
Answer: 50 m
and , so m.
Loads and load combinations: A beam has a permanent load of 3.0 kN/m and an imposed load of 2.0 kN/m. What is the design load in the ultimate limit state (1.2G + 1.5Q)?
Answer: 6.6 kN/m
kN/m.